The project construction period is from 2010 to 2010, with a total investment of RMB 50,200,000. It has now entered the phase of feasibility study (at the time of EIA). The construction content of this project is the use of part of the original equipment of the waste alkali treatment unit of the original cyclohexanone plant and the transformation of the waste alkali treatment unit of the original cyclohexanone plant. Annual processing 45,600 tons of cyclohexanone saponification waste lye. The key equipments include pumps, filters, and waste alkali treatment equipment.